Translate rack IT load into supply requirements with peak facility overhead, losses and power factor; annual efficiency or a bare MW label is insufficient.
The updated AIRR host requirements ask projects to connect an IT-load target to the electrical supply that can support it. This is a useful antidote to treating every capacity number as interchangeable. Rack power, facility overhead and apparent import capacity describe different boundaries and must be connected by an explicit calculation.
Choose the measurement boundary
Start by naming where the IT load is measured and where the supply capacity is specified. Do not add numbers from different boundaries without accounting for the equipment between them. Our proposed worksheet lists rack load, supporting plant and electrical losses as separate entries. Each entry should have a design condition and an evidence source, allowing an engineer to explain how the connection requirement was derived.
Use the peak design condition
The updated specification calls for peak rather than annual-average PUE when sizing the maximum feed. A favorable yearly average cannot establish the required supply on the design-ambient day. Keep the cooling state and IT demand used in the calculation explicit. These are different questions from estimating annual energy consumption. A facility can have an attractive yearly efficiency figure while still needing enough electrical headroom for its most demanding supported condition.
Keep real and apparent power distinct
MW and MVA should remain separate fields. Converting between them requires the applicable power factor and the engineering assumptions at the connection point. Do not reinterpret a connection rating as the same quantity available to GPU racks. Our suggested review also keeps any fallback sizing assumption visibly separate from a site-specific calculation. That distinction matters when comparing candidate locations with different supporting equipment and supply arrangements.
Make the supply claim reproducible
The final record should state the rack load, peak overhead, losses, power-factor assumption and available firm supply. Keep committed capacity separate from a future expansion option. This article does not certify a particular site or interpret a grant award. It explains why a defensible AI-capacity statement needs a calculation across boundaries, so another reviewer can reproduce it and identify which assumption would change the supported IT load.
Sources
- AIRR competition scope and technical requirements, updated 12 November 2026
- AIRR host-site competition, opened 11 November 2026
Related reading
Earn rental income from GPUs
Have idle GPUs or looking to fund AI infrastructure? Retrivium finds a rental platform, sets up the server and helps you assess income and costs with a pilot.