Accept a leased GPU fleet by topology and workload

In this article
THE QUICK TAKE

Make GPU lease acceptance depend on a per-host topology inventory, representative collective tests and agreed treatment of nonconforming machines.

A training startup leases a batch of servers with the same accelerator name and advertised memory. The demonstration ran on a handpicked host. If the rest of the lot has different peer connectivity or placement, the startup may pay for nodes that cannot meet the expected distributed training schedule.

Record a lot identity

Ask the supplier to identify every machine in the proposed lease, its accelerator model and expected topology. Document software and placement assumptions that affect the job. Require a dated mapping from leased identifiers to the tested hosts. A single demonstration machine can establish that one configuration works. It cannot identify which other nodes share the same data path.

Inspect the actual interconnect

NVIDIA documents topology inspection through nvidia-smi and describes when NCCL can use direct peer access. Preserve observations from the customer environment, including the topology matrix and peer access checks appropriate to the device. Compare the reported path with the expected topology. Identical device names on a shopping page do not describe the host bridge, link arrangement or network interface available to a specific training job.

Agree on a workload-shaped test

Use a collective that matters to the training workload, with documented rank placement, message size range and repetitions. NVIDIA publishes NCCL Tests, including an all-reduce test. Save both performance and correctness data for a range of sizes, and run an application smoke job with actual model components. Do not convert a synthetic maximum into a delivery guarantee unless the contract names that exact test.

Treat exceptions as part of the offer

Define who can accept a substitute and what evidence follows a replacement machine. Include a way to hold an anomalous node outside the billable lot while the supplier investigates, if agreed. Test a case where a replacement matches the accelerator inventory but fails the interconnect check. The machine should remain a documented exception until someone approves a workload that it can meet.

Tie the start date to the accepted lot

Make the acceptance report visible to the founder and the infrastructure owner before training starts. Compare the cost of delay with the demonstrated throughput of the accepted machines. A subset can be useful if the workload can be scaled down, but that should be a new approved plan. Keep the test record so the startup can verify that later changes have not silently replaced the original leased configuration.