In this article
Short component-level measurements inform a modeled IT-demand scenario; they do not become a year of observed facility electricity, and the case studies exclude cooling and auxiliaries.
The title Measurement of Generative AI Workload Power Profiles for Whole-Facility Data Center Infrastructure Planning describes a bridge between experiments and planning. The April 2026 study measures selected workloads on the laboratory’s Kestrel cluster, then feeds those profiles into an event-driven simulation. Reading the boundary is essential: the annual case studies exclude cooling and auxiliary loads, so their outputs should not be relabeled as complete metered facility electricity.
What is directly sampled
The experiments use H100 GPU nodes and a software tracker built on device telemetry interfaces. The reported sampling interval is 0.1 seconds. Profiles aggregate CPU and GPU readings for training, fine-tuning and inference workloads. This is finer logging of selected component signals, not an external meter proving that every server or building load is included.
The workloads include language-model fine-tuning, image-model training and serving. Their setup and scale affect the power pattern. In the fine-tuning experiments, keeping work per device fixed changes global batch size as node count grows. Runtime and convergence differences therefore require more interpretation than treating every additional node as an identical reduction in completion time.
A short serving trace is a workload observation
In a finite-request serving benchmark, average power rapidly approaches about 2.9 kW before throughput stops improving proportionally with offered traffic. The authors also collect separate sustained-request snippets over three minutes to feed the simulation. These are different experimental windows, not interchangeable samples of every production service.
Request length, model instances and latency determine what useful work accompanies the power. A flatter power curve does not establish unlimited request capacity or unchanged service quality. The guide to energy per inference explains why workload and completed-output denominators belong alongside a power trace.
What the annual simulation adds
The model combines measured workload profiles with assumed job arrivals, occupancy and service composition. Its training-oriented case schedules jobs, while its serving case allocates request rates among model instances under a latency-related limit. Seasonal and daily patterns are drawn from separate traces and assumptions.
Here utilization means occupied nodes in the model; it is not a GPU sensor’s compute-utilization percentage or power divided by the rated maximum. The simulated 10 MW training-oriented and 1 MW inference examples are defined without cooling and auxiliary loads. Thus the model extends the scale and duration of the measurements but does not directly observe a commercial facility operating for a year.
What a planner can and cannot conclude
The simulation records queues or unsupported requests when activity exceeds the assumed capacity. It therefore makes an important tradeoff visible: serving more demand can alter both energy and the ability to meet the modeled response target. A particular limit and workload mix cannot guarantee another operator’s service level.
The primary publication record and full text are the same author study, not independent replications. Its useful contribution is an explicit path from measured traces to modeled demand with documented assumptions. A complete facility assessment still needs storage, networking, conversion and cooling within an identified accounting boundary. GPU versus server power measurement provides the related hierarchy. These results support scenario analysis, while retaining the distinction between sampled components, modeled IT demand and actual building electricity.