In this article
A delayed application starts after an earlier electrical transition; qualifying inrush requires the actual outlet and supply energization sequence, not scheduler timing alone.
A rack’s jobs are configured to start gradually after boot. Following an input-power interruption, however, its supplies may energize together before any scheduler runs. A careful application startup schedule cannot establish control over that earlier electrical event. Review the actual restoration sequence at the outlet boundary.
Split the startup timeline
Name input restoration, PDU outlet energization, supply startup, host boot and application admission separately. The Raritan power-quality paper describes inrush as increased current when supplies first turn on. That mechanism differs from GPU demand when a running host begins computation. Preserve both events if the acceptance scenario includes them; a delay applied only after the operating system starts cannot retroactively spread supply energization.
Inspect the outlet policy
The manufacturer’s remote-power-control description distinguishes sequencing individual outlets and outlet groups. Establish which supported function the installed model provides and what event invokes it. A software queue, a host boot delay and a PDU restoration policy are different controllers. Retain the effective policy and supported behavior rather than assuming that a feature named sequencing governs every way power can return to the connected equipment.
Map all supplies to the sequence
Include every supply input and its actual outlet group. A server receiving power through another path may not experience the same state transition as its neighbor. The dual-input guide explains the need to preserve both paths. Review whether independently controlled groups can still energize a shared upstream boundary together. Sequencing within one PDU does not, without coordination evidence, establish a rack-wide sequence across several devices.
Choose evidence that resolves the event
Retain suitable outlet-state records and electrical observations from the accepted commissioning sequence. Where the installed equipment supports event-triggered waveform capture, preserve its scope and trigger rather than treating an ordinary dashboard average as equivalent. The sampling guide explains the general limitation of unresolved short events. Repeated software polls cannot prove an unobserved electrical peak was absent, and a later stable reading does not reconstruct its amplitude.
Check restoration and service dependencies
Assess the supported electrical sequence together with the intended boot dependencies. Spreading energization may change when networking or shared storage becomes available; application readiness still needs its own test. Use approved commissioning or an appropriate isolated equivalent, without prescribing outlet switching on occupied systems. Acceptance identifies the actual power-return path, the consumers included and the observed sequence, with unresolved stages explicitly retained rather than filled in from configuration names.
Keep the conclusion bounded
A useful record distinguishes qualified electrical restoration from qualified application admission. It does not infer breaker coordination, universal delay values or an approved electrical connection from a successful software restart. Revisit the evidence after changing relay policy, supply mapping or upstream topology. The key result is knowing which controller acts before host boot and whether the available observations demonstrate its intended sequence, rather than calling a gradual job ramp a measurement of PSU inrush control.