In this article
A liquid-to-liquid CDU thermally couples isolated circuits; differential pump head, static circuit pressure and the other circuit's pressure are different quantities.
A dashboard shows a modest secondary pump differential, and a facility record uses it to approve the CDU’s primary connection. The inference crosses an isolated heat exchanger and changes the measured quantity. Map the pressure boundaries before comparing readings with component limits or claiming either circuit is qualified.
Draw both fluid circuits
The Vertiv CDU100 planning guide describes a secondary sealed loop rejecting heat to an external primary source through a plate exchanger. Preserve the actual primary and secondary paths, their interfaces and connected equipment. Thermal coupling does not make them the same hydraulic circuit. A measurement on the IT side cannot be relabeled as facility-water pressure merely because both paths belong to the same CDU enclosure.
Name the pressure quantity
Distinguish a point’s pressure from a difference between supply and return. Record the measurement locations, reference and units. A pump differential describes the pressure change relevant to circulation; it is not automatically the maximum pressure present anywhere in the sealed loop. The flow-and-rating guide preserves related pressure conditions. Keep the actual sensor contract instead of comparing every field containing pressure with the same component rating.
Resolve each circuit’s limits
The manufacturer describes a primary maximum working-pressure condition independently from secondary flow and differential-pressure performance. Use the applicable installed product’s limits rather than importing values from this example. Include connected hoses, manifolds, fittings and equipment within each path’s supported qualification. The OCP requirements separately identifies operating and burst pressure; a destructive failure boundary is not a normal-service allowance or a target for an acceptance exercise.
Separate thermal success from hydraulic acceptance
An acceptable secondary supply temperature can coexist with unresolved pressure qualification on either side. Heat transfer alone does not establish that the facility path remains within every component’s supported conditions. Likewise, a pressure observation cannot establish sufficient thermal duty. The heat-measurement guide explains why captured heat needs a separately scoped model. Preserve these conclusions together without allowing a successful temperature check to erase a missing hydraulic requirement.
Review the intended operating scenarios
Use approved design and commissioning evidence for normal operation and the supported transitions relevant to the installation. Record which circuit and quantity each observation covers. Acceptance must identify the applicable limits and evidence for both paths, including unresolved transient conditions. This review does not direct pressurization, valve operation or a proof test on occupied equipment. A collector fixture can verify correct labeling but cannot physically qualify the installation’s pressure behavior.
Preserve the boundary after changes
Store the accepted circuit map, component identities and pressure evidence with the change record. Reassess after connecting another rack or changing facility supply conditions. The useful conclusion identifies what each pressure reading establishes and what remains unmeasured. It does not infer primary conditions from secondary pump head, equate normal operating pressure with burst pressure or promise that a hydraulically separated loop is immune to every exchanger fault or unsupported service configuration.